The planning process

Understanding the stages of Heathrow expansion

The information below outlines the key stages of the Development Consent Order (DCO) process, focusing particularly on opportunities for communities to engage and have their say. While presented in sequence, some stages and activities may overlap.

Running alongside

A separate process for airspace design

Alongside the DCO process, future flight paths will be considered through a separate airspace change process, known as CAP 1616. This is being taken forward by the UK Airspace Design Service (UKADS), which is responsible for coordinating airspace redesign across London and southern England, under the oversight of the Civil Aviation Authority (CAA).

As future flight paths have not yet been finalised, communities may not have a complete picture of how aircraft noise could affect their local area, particularly those further from the airport, during consultations on Heathrow expansion proposals.

There will be separate opportunities for communities to have their say on proposed airspace changes. HEICEB is seeking further clarity on the timetable for this process and will provide updates through Heathrow Expansion Watch as more information becomes available.

Complete

1

Publication of proposal

When:
January to July 2025

Having your say:
This stage was not a formal public consultation.

The Government invited proposals for a third runway at Heathrow. Two were put forward.

In January 2025, the Government said it would support proposals for a third runway at Heathrow airport and invited expansion proposals “by the summer”.

Heathrow Airport Limited (HAL)

In July 2025, Heathrow Airport Limited (“HAL”) published, and submitted to Government, their Proposal for Expanding Heathrow Airport – the UK’s Gateway to Growth, which sets out HAL’s plans for the airport’s expansion. It includes:

  • a third runway (of up to 3.5km) located north-west of the existing airport, and associated taxiways designed to deliver up to 276,000 additional flights a year (i.e. an increase from 480,000 to 756,000);

  • a new terminal complex to the west of Terminal 5; and

  • new and upgraded supporting infrastructure (including increasing cargo capacity by 50%, reconfiguring surface access, including the realignment of the M25 below the new runway, and parking facilities).

Heathrow West Limited

Heathrow West Limited, a subsidiary of the Arora Group, has proposed a rival expansion plan that includes:

  • a 2.4 km runway further to the east of the HAL scheme (to be operational by 2035);

  • an option to extend the runway to 3.5km over the M25 after 2040, if necessary;

  • a new Terminal 6, located to the west of Terminal 5, and designed to handle up to 40 million passengers each year;

  • associated airfield infrastructure, surface access and public transport improvements; and

  • a construction approach that avoids building over the M25.

Under way

2

Review of the Airports National Policy Statement

Renamed the Heathrow Expansion National Policy Statement (HENPS).

When:
October 2025 to date. Parliamentary scrutiny runs until 26 November 2026.

Having your say:
The public consultation ran from June to September 2026. It has now closed.

The Government is reviewing the national policy that any expansion proposal will be assessed against.

Key dates

  • 2018: the Airports National Policy Statement (ANPS) is designated.

  • October 2025: a review of the ANPS is launched.

  • June 2026: the Department for Transport publishes the draft Heathrow Expansion National Policy Statement (HENPS).

  • June to September 2026: public consultation on the draft HENPS. This consultation has now closed.

  • Until 26 November 2026: Parliamentary scrutiny. A Parliamentary Select Committee is examining the proposals and will make recommendations to the Government.

  • Next: the Government decides whether to finalise the HENPS. The final policy statement is subject to a vote in the Houses of Parliament before it can take effect.

The four key areas in the draft HENPS

Economic growth and employment opportunities

Air quality

Climate change

Aircraft noise

Worth knowing

The HENPS does not grant planning permission for a third runway.

Any expansion proposal must still undergo a separate planning process to meet the conditions set out in the HENPS before development consent can be granted.

Open now

3

Pre-application engagement

When:
Heathrow Airport Limited: 27 October to 22 December 2026. Heathrow West: currently scheduled for Spring 2027.

Having your say:
Open now. Anyone can take part.

This is an important opportunity for residents to understand and give their views on how expansion could affect their homes, neighbourhoods and everyday lives, and how the plans could be improved before proposals are finalised.

Between 27 October and 22 December 2026, HAL will run their own public consultation, seeking views on expansion. Heathrow West have also committed to consulting as they progress their plans, currently scheduled for Spring 2027.

Communities can use these opportunities to:

  • Review the proposals and understand how they might be affected.

  • Raise concerns or identify potential impacts that may not have been adequately considered.

  • Suggest changes, alternatives or additional measures to reduce adverse effects.

  • Highlight potential benefits and opportunities for local communities.

  • Submit feedback supported by local knowledge and evidence.

Worth knowing

Promoters are no longer legally required to hold a statutory consultation. Although the previous statutory consultation requirements have been removed, feedback remains an important way for communities to seek to influence proposals before they are finalised.

Have your say on Heathrow Airport’s proposals

To come

4

Heathrow expansion proposals finalised following pre-application steps

When:
Before applications are submitted, expected by the end of 2027.

Having your say:
Limited. Promoters may continue engaging as they finalise their proposals.

This stage is important because it brings together the detailed information that will form the basis of the planning application.

Scheme promoters prepare the detailed plans, environmental assessments and supporting documents required for a Development Consent Order application.

To come

5

Proposals submitted to the Planning Inspectorate

When:
Heathrow West expected November 2027. Heathrow Airport Limited expected December 2027. The acceptance decision follows within 28 days.

Having your say:
Not at this stage. Application documents are made public to read.

At this stage of the potential Heathrow expansion, the relevant proposal, in the form of an application for development consent, will be submitted to the Planning Inspectorate for acceptance.

Worth knowing

Acceptance does not mean that the expansion proposals have been approved. It means the application can proceed to the next stage of the planning process, where its merits will be examined in detail.

To come

6

Pre-Examination phase: registration of Interested Parties

When:
After an application is accepted. Registration typically lasts around 5 to 6 weeks.

Having your say:
Yes. Register as an Interested Party before the published deadline.

Once the Planning Inspectorate accepts the DCO application, the application enters the pre-Examination stage. This is a key opportunity for individuals, community groups, local authorities, and other stakeholders to register as “Interested Parties” for the upcoming Examination of the application.

1

Registration opens

The Planning Inspectorate opens a registration period, typically lasting around 5 to 6 weeks, during which time those interested can register to participate.

2

How to register

Registration is done online, on the relevant project page on the Planning Inspectorate’s website. Registrants must provide their contact details and submit a summary (known as a Relevant Representation) outlining their main points of concern, support, or interest in the proposal.

3

Becoming an “Interested Party”

Once registered, you gain the legal status of an Interested Party.

Worth knowing

It is important to register before the published deadline. People who do not register may have fewer opportunities to participate formally in the examination.

To come

7

Examination of the DCO application

When:
Lasts 6 months, starting the day after the close of the Preliminary Meeting.

Having your say:
Yes, for Interested Parties: written representations and hearings.

The Examination is the review stage for DCO applications. It is primarily a written process, though there will be hearings.

Three kinds of hearing

Issue-Specific Hearings

For complex or technical matters.

Compulsory Acquisition Hearing

For anyone who owns land, holds rights over land, or has an interest in land the Applicant is seeking to acquire or use temporarily.

Open-Floor Hearings

An opportunity for the public to speak on matters included in their Relevant Representation.

Worth knowing

Every deadline in the Examination timetable is strict, and it is important that a document is submitted by the relevant deadline. To participate as a speaker at a hearing, it is essential to register in advance.

To come

8

The Examining Authority prepares its report and recommendation to the Secretary of State

When:
Three months from the close of the Examination.

Having your say:
Generally closed, unless the Secretary of State requests more information.

The Examining Authority considers the evidence presented during the Examination and prepares a detailed report and recommendation for the Secretary of State.

Worth knowing

The Examining Authority makes a recommendation, not the final decision. That responsibility rests with the Secretary of State for Transport.

To come

9

Secretary of State’s decision

When:
Within 3 months of receiving the report. The deadline can be extended.

Having your say:
No. A decision can be challenged only by judicial review, within 6 weeks.

After the Examining Authority has sent the report and recommendation to the Secretary of State, the DCO application will be determined by the Secretary of State. This is when consent will be granted or refused.

To come

10

Implementation in line with requirements

When:
After development consent is granted.

Having your say:
Yes, as construction progresses, and through the separate airspace change process.

If the Secretary of State grants development consent for a DCO application, the process moves into implementation. The project can start to be delivered, but only in accordance with the DCO and its “requirements”.